VASAVI SKYLA is a new residential project by VASAVI HOMES LLP in Kondapur, Ranga Reddy district, Greater Hyderabad. It is registered with the Telangana RERA register under competent authority GHMC. As of 23 Nov 2026, promoter-filed construction progress is 12%. The proposed completion date is 22/03/2028. Of 726 units, 355 are booked (48% absorption). Approved built-up area is 2,603,312 sq ft.
Sales velocity & absorption Steady
5.92units / month (since registration)
48%absorption (355/726 booked)
60.0months on market
Booking data maintained · velocity = booked units ÷ months since RERA registration. Promoter-filed; verify on the official portal.
Construction progress
12% complete (promoter-filed RERA activity-wise progress) · stage: Early (1–25%)
DistrictRanga Reddy
StatusNew Project
TypeResidential
LocalityKondapur
Pin500032
AuthorityGHMC
Plan approval—
Registered22/11/2021
Proposed completion22/03/2028
Plot area (sqft)264,285
Built-up (sqft)2,603,312
Max floors32
Total units726
Configuration mix
| Configuration | Units (approx) |
|---|---|
| 3 BHK | 356 |
| 4 BHK | 362 |
Declared amenities
Internal Roads & FootpathsWater SupplySewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsGreen Strip/TOT LOT/ParkStreet LightingCommunity BuildingsTreatment And Disposal Of Sewage And Sullage WaterSolid Waste Management And DisposalWater Conservation, Rain water HarvestingEnergy managementFire Protection And Fire Safety RequirementsElectrical Meter Room, Sub-Station, Receiving StationAggregate area of recreational Open Space
Project professionals
ArchitectM Jayanand (RERA)
Structural engineerG Sampath Kumar (RERA)
This is promoter-filed RERA information compiled from the official Telangana RERA register for research. Verify current status, approvals, booked counts and litigation on the official portal rera.telangana.gov.in before any transaction.