Narsingi Village · Ranga Reddy New

TUBEROSE

by ANANDA HOMES

TUBEROSE is a new residential project by ANANDA HOMES in Narsingi Village, Ranga Reddy district, Greater Hyderabad. It is registered with the Telangana RERA register under competent authority HMDA (plan approval 022545/SKP/R1/U6/HMD). As of 23 Nov 2026, promoter-filed construction progress is 52%. The proposed completion date is 04/02/2025. Of 85 units, 21 are booked (24% absorption). Approved built-up area is 103,579 sq ft.

Sales velocity & absorption Slow

0.3units / month (since registration)
24%absorption (21/85 booked)
69.6months on market

Booking data maintained · velocity = booked units ÷ months since RERA registration. Promoter-filed; verify on the official portal.

Construction progress

52% complete (promoter-filed RERA activity-wise progress) · stage: Advanced (51–75%)

DistrictRanga Reddy
StatusNew Project
TypeResidential
LocalityNarsingi Village
Pin502302
AuthorityHMDA
Plan approval022545/SKP/R1/U6/HMD
Registered04/02/2021
Proposed completion04/02/2025
Plot area (sqft)41,411
Built-up (sqft)103,579
Max floors7
Total units85

Configuration mix

ConfigurationUnits (approx)
2 BHK65
3 BHK20

Declared amenities

Internal Roads & FootpathsWater SupplySewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsGreen Strip/TOT LOT/ParkStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingEnergy managementFire Protection And Fire Safety RequirementsElectrical Meter Room, Sub-Station, Receiving Station

Project professionals

ArchitectVISHEWANTHAM BALA BHARGAVI
Structural engineerNARAYANADAS VAMSHI KRISHNA
This is promoter-filed RERA information compiled from the official Telangana RERA register for research. Verify current status, approvals, booked counts and litigation on the official portal rera.telangana.gov.in before any transaction.