SOBHA WATER FRONT is a new residential project by SOBHA LIMITED in Somajiguda, Hyderabad district, Greater Hyderabad. It is registered with the Telangana RERA register under competent authority Plan Approval Number. As of 23 Nov 2026, promoter-filed construction progress is 53%. The proposed completion date is 28/02/2029. Of 60 units, 23 are booked (38% absorption). Approved built-up area is 633,615 sq ft.
Sales velocity & absorption Fast-moving
20.91units / month (since registration)
38%absorption (23/60 booked)
1.1months on market
Booking data maintained · velocity = booked units ÷ months since RERA registration. Promoter-filed; verify on the official portal.
Construction progress
53% complete (promoter-filed RERA activity-wise progress) · stage: Advanced (51–75%)
DistrictHyderabad
StatusNew Project
TypeResidential
LocalitySomajiguda
Pin500082
AuthorityPlan Approval Number
Plan approval—
Registered21/10/2026
Proposed completion28/02/2029
Plot area (sqft)174,268
Built-up (sqft)633,615
Max floors15
Total units60
Configuration mix
| Configuration | Units (approx) |
|---|---|
| 3 BHK | 1 |
| 5 BHK | 59 |
Declared amenities
Water Conservation, Rain water HarvestingEnergy managementFire Protection And Fire Safety RequirementsElectrical Meter Room, Sub-Station, Receiving StationAggregate area of recreational Open SpaceInternal Roads & FootpathsWater SupplySewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsGreen Strip/TOT LOT/ParkStreet LightingCommunity BuildingsTreatment And Disposal Of Sewage And Sullage WaterSolid Waste Management And Disposal
Project professionals
ArchitectBASITH ALI
Structural engineerMOHAMMED MAQSOOD ANSARI
This is promoter-filed RERA information compiled from the official Telangana RERA register for research. Verify current status, approvals, booked counts and litigation on the official portal rera.telangana.gov.in before any transaction.