NMR FLEMINGO is a on-going residential project by NMR PROJECTS in Karmanghat, Ranga Reddy district, Greater Hyderabad. It is registered with the Telangana RERA register under competent authority GHMC (plan approval 2/C3/11502/2017). As of 23 Nov 2026, promoter-filed construction progress is 32%. The proposed completion date is 23/11/2023. Of 20 units, 3 are booked (15% absorption). Approved built-up area is 20,828 sq ft.
Sales velocity & absorption Stalled
—units / month (since registration)
15%absorption (3/20 booked)
—months on market
Booking data maintained · velocity = booked units ÷ months since RERA registration. Promoter-filed; verify on the official portal.
Construction progress
32% complete (promoter-filed RERA activity-wise progress) · stage: Mid (26–50%)
DistrictRanga Reddy
StatusOn-Going Project
TypeResidential
LocalityKarmanghat
Pin500035
AuthorityGHMC
Plan approval2/C3/11502/2017
RegisteredProposed
Proposed completion23/11/2023
Plot area (sqft)7,920
Built-up (sqft)20,828
Max floors5
Total units20
Configuration mix
| Configuration | Units (approx) |
|---|---|
| 2 BHK | 20 |
Declared amenities
Water SupplySewerage (Chamber, Lines, Septic Tank , STP)Green Strip/TOT LOT/ParkWater Conservation, Rain water HarvestingEnergy managementElectrical Meter Room, Sub-Station, Receiving Station
Project professionals
ArchitectBASITH ALI
Structural engineerI MADHAVA RAO