Home›Greater Hyderabad RERA›Luckie Township Phase-II
Kothur · Ranga Reddy New

Luckie Township Phase-II

by SWATHI PROMOTERS PRIVATE LIMITED

Luckie Township Phase-II is a new plotted development project by SWATHI PROMOTERS PRIVATE LIMITED in Kothur, Ranga Reddy district, Greater Hyderabad. It is registered with the Telangana RERA register under competent authority HMDA (plan approval 000284/LO/Plg/HMDA/2). As of 23 Nov 2026, promoter-filed construction progress is 42%. The proposed completion date is 31/07/2024. Approved built-up area is 327,012 sq ft.

Construction progress

42% complete (promoter-filed RERA activity-wise progress) · stage: Mid (26–50%)

DistrictRanga Reddy
StatusNew Project
TypePlotted Development
LocalityKothur
Pin509228
AuthorityHMDA
Plan approval000284/LO/Plg/HMDA/2
Registered31/07/2021
Proposed completion31/07/2024
Plot area (sqft)502,022
Built-up (sqft)327,012
Max floors—
Total units0

Declared amenities

Internal Roads & FootpathsWater SupplySewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsGreen Strip/TOT LOT/ParkStreet LightingWater Conservation, Rain water HarvestingElectrical Meter Room, Sub-Station, Receiving Station

Project professionals

ArchitectRAJESH N
Structural engineerD MANASA
This is promoter-filed RERA information compiled from the official Telangana RERA register for research. Verify current status, approvals, booked counts and litigation on the official portal rera.telangana.gov.in before any transaction.

More by SWATHI PROMOTERS PRIVATE LIMITED →   More in Kothur →   All projects →