GREEN VALLEY BLOCK - B is a on-going residential project by JAYA RAMI ARANI in Kondapur, Ranga Reddy district, Greater Hyderabad. It is registered with the Telangana RERA register under competent authority GHMC. As of 23 Nov 2026, promoter-filed construction progress is 7%. The proposed completion date is 14/03/2020. Approved built-up area is 79,536 sq ft.
Sales velocity & absorption No sales filed
0.0units / month (since registration)
0%absorption (0/55 booked)
105.7months on market
Booked count filed as 0 (often not updated) · velocity = booked units ÷ months since RERA registration. Promoter-filed; verify on the official portal.
Construction progress
7% complete (promoter-filed RERA activity-wise progress) · stage: Early (1–25%)
DistrictRanga Reddy
StatusOn-Going Project
TypeResidential
LocalityKondapur
Pin500084
AuthorityGHMC
Plan approval—
Registered01/02/2018
Proposed completion14/03/2020
Plot area (sqft)26,827
Built-up (sqft)79,536
Max floors6
Total units55
Configuration mix
| Configuration | Units (approx) |
|---|---|
| 2 BHK | 45 |
| 3 BHK | 10 |
Declared amenities
Internal Roads & FootpathsWater SupplySewerage (Chamber, Lines, Septic Tank , STP)Green Strip/TOT LOT/ParkStreet LightingWater Conservation, Rain water HarvestingFire Protection And Fire Safety RequirementsElectrical Meter Room, Sub-Station, Receiving Station
Project professionals
ArchitectRAVI KUMAR POLASA
Structural engineerT CHANDRA OBULA REDDY
This is promoter-filed RERA information compiled from the official Telangana RERA register for research. Verify current status, approvals, booked counts and litigation on the official portal rera.telangana.gov.in before any transaction.