Narrashalapally · Ranga Reddy New

ARAO ETERNA

by ABHINANDAN RAO PUPPALA

ARAO ETERNA is a new residential project by ABHINANDAN RAO PUPPALA in Narrashalapally, Ranga Reddy district, Greater Hyderabad. It is registered with the Telangana RERA register under competent authority DTCP (plan approval 3015/W5/2019/1851). As of 23 Nov 2026, promoter-filed construction progress is 43%. The proposed completion date is 29/01/2026. Approved built-up area is 161,509 sq ft.

Sales velocity & absorption No sales filed

0.0units / month (since registration)
0%absorption (0/99 booked)
81.8months on market

Booked count filed as 0 (often not updated) · velocity = booked units ÷ months since RERA registration. Promoter-filed; verify on the official portal.

Construction progress

43% complete (promoter-filed RERA activity-wise progress) · stage: Mid (26–50%)

DistrictRanga Reddy
StatusNew Project
TypeResidential
LocalityNarrashalapally
Pin500055
AuthorityDTCP
Plan approval3015/W5/2019/1851
Registered29/01/2020
Proposed completion29/01/2026
Plot area (sqft)43,271
Built-up (sqft)161,509
Max floors7
Total units99

Configuration mix

ConfigurationUnits (approx)
2 BHK71
3 BHK22
4 BHK6

Declared amenities

Water SupplySewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsGreen Strip/TOT LOT/ParkWater Conservation, Rain water HarvestingElectrical Meter Room, Sub-Station, Receiving Station

Project professionals

ArchitectMuppana Kiran Kumar
Structural engineerZaki Ahmed